The excavator is removing the asphalt paving where the remainder of curbs will be placed. They are grading for the sidewalks that will be poured this week or next as weather permits. The excavator will then finish grade the site in preparation for sod and seeding. The trees will be planted later in the spring.
The masonry contractor is cleaning the brick on the Parish Hall. Installation of the windows will begin as soon as the masons complete the cleaning. The window frames are in town and the glass will follow immediately.
The ceramic floor tile has been delivered and a mockup has been laid for the Architect’s approval. Upon approval the tile in the kitchen and restrooms will be placed. Most of the drywall in the Parish Hall has been installed and is being taped. The drywall contractor will start installation of drywall in the Narthex this week. The electricians will have removed all the existing electrical systems from the existing Electrical Room and the new systems will be utilized. We are preparing the opening from the Narthex into the Parish Hall. The overhead tracks for the folding partitions in the Parish Hall will be installed this week.
When the drywall work is completed in the Narthex, the contractor will sheet rock the Sacristy.
Weldon Fate, Building Chairman