The brick manufacturer has been overhauling the kilns in their plant this winter. The plant will reopen the first of March and the remaining brick for our project will be at the jobsite by the third week in March. When the weather permits, it will take less than a week to complete all the masonry. The contractor will be working on other exterior work such as landscaping, sidewalks and curbs as the weather permits.
Heating and Air Conditioning units have been installed in the Sanctuary and drywall work is proceeding. The rough-in electrical work there is mostly complete. A thirty-gallon water heater has been installed above the ceiling in the Sanctuary. This will provide hot water for the sinks in the Sacristy.
In the Parish Hall, sheetrock work is complete in the kitchen and bathrooms. The Drywall Contractor is installing sheetrock in the Parish Hall. Windows and doors have been measured and will be installed in the near future. The electrical rough-in for the audio/visual system in the Parish Hall has been installed.
Metal studs, electrical and mechanical rough-in is mostly complete in the Narthex. Sheetrock work in the Narthex will commence as soon as the Parish Hall sheetrock is done.
Weldon L. Fate, Building Chairman