The asphalt paving in the parking lot is complete. We will have a net gain in parking spaces. We can park in the main lot or along the Antioch driveway. Both entrances to the Narthex will be open for Sunday services. The seal coat and parking stall striping will be done in the spring when all exterior work is complete. The Electrical Contractor has poured the light pole bases along the driveways and will be installing the light poles in the near future.
The waterproofing contractor has started waterproofing the exterior walls of the building. The finish waterproofing product will be sprayed on the exterior sheathing and should prevent any air of water leakage. When this work is completed, the masonry work will commence. The roofing contractor has started work on the roof. The Parish hall will be completed first and then the roof over the kitchen area will be installed.
The plumbing, fire protection and electrical rough-in work is proceeding on the interior of the building.
The Narthex will remain as it is for a few weeks. The floor will have to be levelled before we can proceed with the finish work. Forgive us for the temporary inconvenience!
Weldon L. Fate—Building Chairman