The Excavator is grading around the site and spreading topsoil so we will be able to see how the landscaped and grass areas will look in the spring. The sidewalks along 123rd and the concrete pad in front of the dumpster enclosure will be completed this week.
Brickwork and roofing are complete on the Sacristy. Brickwork is continuing on the Parish hall and will be finished as weather permits. The window and door openings have been closed with temporary plastic closures. This allows the contractor to heat the new building and interior work can be completed..
They are installing sheetrock in the kitchen and restrooms this week. The fire protection lines have been run in the Parish Hall. The Plumbing, HVAC and electrical Contractors are all working in the Parish Hall. The electrical room has been sheetrocked and painted to allow electrical panels to be installed.
The sub floor in the existing Narthex has been levelled and cured. Feel free to walk on this floor.
The new parking lot lights have been installed and will be operational soon.
Weldon L. Fate, Building Chairman