This coming week the contractor will asphalt the new driveway and sewer line excavations. If you come to the church Monday through Friday, be aware that you may not be able to park next to the church as before, but rather near the existing driveway entrance. Look for cones to alert where you must not enter.
After the asphalt is poured, the new driveway will be open. The old driveway will be torn up at the end of the week. Take care when you drive in from 123rd Street and when you drive on the new paving. Also be watchful of the new islands which are along both sides of the existing north/south island in the middle of the parking lot.
The second phase of asphalting will be the new parking areas where the storage shed is located, and also northwest of the church near Antioch Rd.
The floor slab of the parish hall has been poured, and structural steel framing is scheduled to start on Monday.
The playground has been completed.
Remember, drive carefully on the new asphalt and take care around the new curbs. The lot will be re-striped in the near future.
Weldon Fate, Building Chairman