The weather is starting to improve and we will see more activity on the site. The contractor is pouring sidewalks and curbs on the Antioch side of the church. There is also a new sidewalk at the Sacristy. When all the walks and curbs are in, the site will be graded and made ready for landscaping and seeing later in the spring. The junior Warden is interviewing Lawn Sprinkler Contractors to secure prices for a watering system to be installed this spring.
The sheetrock is almost complete in the Narthex and has been started in the Sacristy.
The quarry tile is complete in the Parish hall restrooms and has been started in the kitchen. The fire door between the Parish Hall and Narthex has been completed. Installation of windows in the Parish Hall is scheduled to start on Friday and should take about a week. The tracks for the folding partitions dividing the Parish Hall have been installed. The projection screens are scheduled for next week.
The project is on schedule to be completed in the early spring.
Weldon Fate, Building Chairman