We are getting close to completion. The latest snowfall will delay the cleanup and final grading of the site. The landscape contractor and the irrigation contractor will begin work in April when the weather will be more cooperative.
The wood doors and door hardware will be delivered this week and installation of the doors will begin next week. The paneling for the Parish Hall will be installed next week. The remainder of the countertops and casework will be installed next week. The carpenters have installed the wood base in the Narthex and carpet will be installed this week. The aluminum entrances are complete in the Narthex and the temporary door into the Office Area has been removed. The broken window in the Parish Hall has been replaced.
The ceiling contractor is installing ceiling tiles throughout the project. The sprinkler contractor is testing the sprinkler pipe system for any leaks and will install sprinkler heads this week. The electrical contractor is installing light fixtures throughout the project. Final painting and cleanup will take place next week.
The brick to finish the project has been made and is available for delivery when the weather clears. The brick on the Antioch side will be completed as soon as weather allows. The contractor will apply to the City of Overland Park for a Temporary Certificate of Occupancy in the next few weeks. We will be ready for the Bishop’s visit in May.