This week the sheathing on the exterior walls will be installed. The drywall contractor has begun to erect the metal studs for the interior walls. The plumbing contractor will start the plumbing tough-in in the kitchen and bathrooms. The gas main and new electrical transformer will have been installed. The ceramic floor tile in the narthex will be removed October 29. This will be a noisy and dusty process for a couple of days. If the main entries are blocked, please enter through the existing parish hall (Assembly Room) door.
On the exterior, the contractor will pour the slabs in the parking lot islands. The old driveway has been removed. Sealing and stall striping of the parking lot will be accomplished in the spring.
Weldon Fate
Building Chairman